Affected Unit |
Published Date/Time |
Event Type |
Event Status |
Event Start Date/Time (GMT) |
Event End Date/Time (GMT) |
Available Capacity |
Cause |
Related Information |
T_LAGA-1 |
31/08/2022 01:53AM |
Unplanned |
Production unavailability - Active |
30/08/2022 22:30PM |
31/08/2022 01:00AM |
0 |
|
ST LP CV proportional valve replacement |
T_LAGA-1 |
24/08/2022 14:28PM |
Planned |
Production unavailability - Active |
24/08/2022 13:00PM |
24/08/2022 13:30PM |
400 |
Gas Turbine |
|
T_LAGA-1 |
10/08/2022 13:48PM |
Unplanned |
Production unavailability - Active |
10/08/2022 11:30AM |
10/08/2022 13:30PM |
0 |
Turbine |
|
T_LAGA-1 |
03/08/2022 12:08PM |
Planned |
Production unavailability - Active |
02/08/2022 20:30PM |
03/08/2022 11:30AM |
0 |
Steam Turbine |
ST Additional balance weights fitted, vibration |
T_LAGA-1 |
02/08/2022 10:18AM |
Planned |
Production unavailability - Active |
01/08/2022 13:00PM |
01/08/2022 23:30PM |
800 |
Commissioning - Variable Output |
ST Commissioning run after balance weight adjustments for high vibrations |
T_LAGA-1 |
02/08/2022 01:08AM |
Planned |
Production unavailability - Dismissed |
02/08/2022 13:00PM |
07/08/2022 22:00PM |
0 |
Steam Turbine |
ST Vibration investigations |
T_LAGA-1 |
02/08/2022 00:51AM |
Planned |
Superseded |
02/08/2022 13:00PM |
07/08/2022 22:00PM |
800 |
Outage Ends |
|