Affected Unit |
Published Date/Time |
Event Type |
Event Status |
Event Start Date/Time (GMT) |
Event End Date/Time (GMT) |
Available Capacity |
Cause |
Related Information |
T_LAGA-1 |
20/02/2025 00:58AM |
Planned |
Production unavailability - Active |
15/02/2025 03:00AM |
20/02/2025 01:00AM |
410 |
Boiler |
HRSG 12 - tube repairs. |
T_LAGA-1 |
14/02/2025 11:58AM |
Unplanned |
Production unavailability - Active |
14/02/2025 05:30AM |
14/02/2025 12:00PM |
400 |
Turbine |
GT12 trip. |
T_LAGA-1 |
12/02/2025 00:13AM |
Unplanned |
Production unavailability - Active |
11/02/2025 22:00PM |
12/02/2025 04:00AM |
0 |
Steam Turbine |
|
T_LAGA-1 |
11/02/2025 05:23AM |
Unplanned |
Production unavailability - Active |
11/02/2025 05:30AM |
11/02/2025 06:00AM |
166 |
Turbine |
|
T_LAGA-1 |
08/02/2025 11:33AM |
Unplanned |
Production unavailability - Active |
08/02/2025 08:00AM |
08/02/2025 19:00PM |
400 |
Turbine |
|
T_LAGA-1 |
03/02/2025 22:28PM |
Planned |
Production unavailability - Active |
03/02/2025 19:30PM |
03/02/2025 23:00PM |
0 |
Planned Outage |
DCS Logic Upload |