Affected Unit |
Published Date/Time |
Event Type |
Event Status |
Event Start Date/Time (GMT) |
Event End Date/Time (GMT) |
Available Capacity |
Cause |
Related Information |
T_LAGA-1 |
10/01/2025 15:28PM |
Planned |
Production unavailability - Active |
12/01/2025 00:00AM |
12/01/2025 04:00AM |
0 |
Planned Outage |
DCS Logic Upload |
T_LAGA-1 |
08/01/2025 07:08AM |
Unplanned |
Production unavailability - Active |
08/01/2025 07:00AM |
08/01/2025 07:30AM |
100 |
Generator |
ST generator failing to syncronise to grid. |
T_LAGA-1 |
07/01/2025 06:38AM |
Unplanned |
Production unavailability - Active |
07/01/2025 06:00AM |
07/01/2025 06:30AM |
165 |
Turbine |
|
T_LAGA-1 |
07/01/2025 05:53AM |
Unplanned |
Production unavailability - Active |
07/01/2025 05:00AM |
07/01/2025 06:00AM |
165 |
Turbine |
|