Affected Unit |
Published Date/Time |
Event Type |
Event Status |
Event Start Date/Time (GMT) |
Event End Date/Time (GMT) |
Available Capacity |
Cause |
Related Information |
T_LAGA-1 |
26/03/2020 13:14PM |
Unplanned |
Completed |
26/03/2020 13:11PM |
26/03/2020 13:12PM |
813 |
Gas Turbine |
|
T_LAGA-1 |
26/03/2020 11:33AM |
Unplanned |
Ongoing |
26/03/2020 11:30AM |
26/03/2020 15:00PM |
408 |
Gas Turbine |
|
T_LAGA-1 |
26/03/2020 08:44AM |
Unplanned |
Ongoing |
26/03/2020 08:42AM |
26/03/2020 12:30PM |
408 |
Gas Turbine |
|
T_LAGA-1 |
26/03/2020 06:29AM |
Unplanned |
Ongoing |
26/03/2020 06:30AM |
26/03/2020 10:30AM |
408 |
Gas Turbine |
|
T_LAGA-1 |
13/03/2020 16:52PM |
Planned |
Completed |
13/03/2020 18:00PM |
13/03/2020 21:00PM |
824 |
Commissioning - Variable Output |
Commissioning completed early |
T_LAGA-1 |
13/03/2020 16:31PM |
Unplanned |
Superseded |
13/03/2020 21:00PM |
14/03/2020 23:59PM |
824 |
Gas Turbine |
Technical issue resolved prior to REMIT starting. |
T_LAGA-1 |
13/03/2020 10:33AM |
Unplanned |
Ongoing |
13/03/2020 21:00PM |
14/03/2020 23:59PM |
400 |
Gas Turbine |
|
T_LAGA-1 |
12/03/2020 21:31PM |
Planned |
Superseded |
12/03/2020 23:30PM |
13/03/2020 08:00AM |
0 |
Commissioning - Variable Output |
|
T_LAGA-1 |
04/03/2020 15:35PM |
Planned |
Ongoing |
12/03/2020 21:00PM |
13/03/2020 21:00PM |
800 |
Commissioning - Variable Output |
Autotune commissioning, variable output up to 800MW |
T_LAGA-1 |
04/03/2020 15:32PM |
Planned |
Ongoing |
08/03/2020 23:00PM |
09/03/2020 23:00PM |
400 |
Boiler |
|
T_LAGA-1 |
04/03/2020 15:29PM |
Unplanned |
Ongoing |
05/03/2020 21:00PM |
06/03/2020 21:00PM |
400 |
Gas Turbine |
|
T_LAGA-1 |
27/02/2020 11:29AM |
Unplanned |
Ongoing |
02/03/2020 23:00PM |
05/03/2020 21:00PM |
400 |
Gas Turbine |
|
T_LAGA-1 |
25/02/2020 18:02PM |
Unplanned |
Superseded |
01/03/2020 23:00PM |
02/03/2020 23:00PM |
400 |
Gas Turbine |
|
T_LAGA-1 |
11/02/2020 11:50AM |
Planned |
Future |
08/03/2020 23:05PM |
12/03/2020 21:00PM |
800 |
Commissioning - Variable Output |
Autotune commissioning, variable output up to 800MW |
T_LAGA-1 |
11/02/2020 11:47AM |
Planned |
Future |
05/03/2020 21:00PM |
08/03/2020 23:00PM |
0 |
Gas Turbine |
Autotune Install on both GT's |