(UMM)

Affected Unit Published Date/Time Event Type Event Status Event Start Date/Time (GMT) Event End Date/Time (GMT) Available Capacity Cause Related Information
E_LYNE1 01/04/2021
09:43AM
Unplanned Production unavailability - Active 31/03/2021
22:30PM
01/04/2021
08:30AM
130 Plant Available
E_LYNE1 31/03/2021
22:43PM
Unplanned Production unavailability - Active 31/03/2021
22:00PM
31/03/2021
22:30PM
130 Plant Available
E_LYNE1 31/03/2021
22:38PM
Unplanned Production unavailability - Active 31/03/2021
21:30PM
31/03/2021
22:00PM
115 Fuel Handling System
E_LYNE1 29/03/2021
20:04PM
Unplanned Production unavailability - Active 29/03/2021
20:00PM
31/03/2021
12:00PM
130 Plant Available
E_LYNE1 29/03/2021
20:04PM
Unplanned Production unavailability - Active 21/03/2021
19:00PM
29/03/2021
18:30PM
130 Plant Available
E_LYNE1 29/03/2021
20:04PM
Unplanned Production unavailability - Active 29/03/2021
18:30PM
29/03/2021
20:00PM
127 Plant Available
E_LYNE1 18/03/2021
19:48PM
Unplanned Production unavailability - Active 18/03/2021
19:30PM
20/03/2021
21:00PM
130 Plant Available
E_LYNE1 18/03/2021
19:48PM
Unplanned Production unavailability - Active 18/03/2021
08:30AM
18/03/2021
19:30PM
127 Plant Available
E_LYNE1 18/03/2021
08:33AM
Unplanned Production unavailability - Active 18/03/2021
06:30AM
18/03/2021
08:30AM
120 Plant Available
E_LYNE1 18/03/2021
04:33AM
Unplanned Production unavailability - Active 18/03/2021
04:00AM
18/03/2021
06:00AM
97 Milling Plant
E_LYNE1 18/03/2021
04:33AM
Unplanned Production unavailability - Active 18/03/2021
06:00AM
18/03/2021
06:30AM
97 Milling Plant
E_LYNE1 18/03/2021
01:28AM
Unplanned Production unavailability - Active 18/03/2021
01:00AM
18/03/2021
03:30AM
0 Milling Plant
E_LYNE1 18/03/2021
01:28AM
Unplanned Production unavailability - Active 18/03/2021
03:30AM
18/03/2021
04:00AM
120 Milling Plant
E_LYNE1 18/03/2021
00:53AM
Unplanned Production unavailability - Active 16/03/2021
23:00PM
18/03/2021
01:00AM
0 Milling Plant
E_LYNE1 18/03/2021
00:53AM
Unplanned Production unavailability - Active 18/03/2021
03:00AM
18/03/2021
03:30AM
0 Plant Available Event automatically withdrawn.
E_LYNE1 17/03/2021
23:28PM
Unplanned Production unavailability - Active 18/03/2021
03:30AM
18/03/2021
05:00AM
120 Plant Available
E_LYNE1 17/03/2021
22:13PM
Unplanned Production unavailability - Dismissed 17/03/2021
23:00PM
18/03/2021
00:00AM
0 Plant Available Event automatically withdrawn.
E_LYNE1 16/03/2021
22:28PM
Unplanned Production unavailability - Active 17/03/2021
00:00AM
17/03/2021
01:00AM
60 Milling Plant Event automatically withdrawn.
E_LYNE1 16/03/2021
22:28PM
Unplanned Production unavailability - Active 16/03/2021
22:00PM
16/03/2021
23:00PM
80 Milling Plant
E_LYNE1 16/03/2021
22:28PM
Unplanned Production unavailability - Active 16/03/2021
21:30PM
16/03/2021
22:00PM
60 Milling Plant
E_LYNE1 16/03/2021
22:28PM
Unplanned Production unavailability - Dismissed 17/03/2021
01:00AM
17/03/2021
02:00AM
0 Plant Available Event automatically withdrawn.
E_LYNE1 16/03/2021
21:58PM
Unplanned Production unavailability - Dismissed 16/03/2021
23:00PM
17/03/2021
00:00AM
96 Plant Available Event automatically withdrawn.
E_LYNE1 16/03/2021
21:53PM
Unplanned Production unavailability - Active 14/03/2021
11:30AM
16/03/2021
21:30PM
96 Plant Available
E_LYNE1 16/03/2021
17:58PM
Unplanned Production unavailability - Active 17/03/2021
00:00AM
17/03/2021
02:00AM
0 Plant Available
E_LYNE1 14/03/2021
11:33AM
Unplanned Production unavailability - Dismissed 14/03/2021
12:00PM
15/03/2021
00:00AM
98 Plant Available Event automatically withdrawn.
E_LYNE1 14/03/2021
11:33AM
Unplanned Production unavailability - Active 13/03/2021
10:30AM
14/03/2021
11:30AM
96 Milling Plant
E_LYNE1 13/03/2021
10:58AM
Unplanned Production unavailability - Active 12/03/2021
19:30PM
13/03/2021
10:30AM
98 Plant Available
E_LYNE1 12/03/2021
19:43PM
Unplanned Production unavailability - Dismissed 12/03/2021
23:30PM
13/03/2021
14:30PM
90 Plant Available Event automatically withdrawn.
E_LYNE1 12/03/2021
19:43PM
Unplanned Production unavailability - Active 12/03/2021
15:30PM
12/03/2021
19:30PM
94 Plant Available
E_LYNE1 12/03/2021
15:53PM
Unplanned Production unavailability - Active 12/03/2021
15:00PM
12/03/2021
15:30PM
90 Plant Available
E_LYNE1 12/03/2021
14:38PM
Unplanned Production unavailability - Active 12/03/2021
14:30PM
12/03/2021
15:00PM
108 Plant Available
E_LYNE1 12/03/2021
14:38PM
Unplanned Production unavailability - Active 12/03/2021
13:00PM
12/03/2021
14:30PM
90 Plant Available
E_LYNE1 12/03/2021
13:18PM
Unplanned Production unavailability - Dismissed 12/03/2021
13:30PM
13/03/2021
04:00AM
100 Plant Available Event automatically withdrawn.
E_LYNE1 12/03/2021
12:08PM
Unplanned Production unavailability - Active 12/03/2021
13:00PM
12/03/2021
13:30PM
3 Plant Available
E_LYNE1 12/03/2021
12:08PM
Unplanned Production unavailability - Active 12/03/2021
12:30PM
12/03/2021
13:00PM
90 Milling Plant
E_LYNE1 12/03/2021
12:03PM
Unplanned Production unavailability - Active 12/03/2021
12:00PM
12/03/2021
12:30PM
80 Milling Plant
E_LYNE1 12/03/2021
12:03PM
Unplanned Production unavailability - Active 12/03/2021
10:00AM
12/03/2021
12:00PM
3 Plant Available
E_LYNE1 12/03/2021
09:53AM
Unplanned Production unavailability - Active 12/03/2021
09:00AM
12/03/2021
10:00AM
3 Plant Available
E_LYNE1 12/03/2021
09:33AM
Unplanned Production unavailability - Dismissed 12/03/2021
10:00AM
12/03/2021
12:00PM
0 Plant Available Event automatically withdrawn.
E_LYNE1 12/03/2021
08:18AM
Unplanned Production unavailability - Active 12/03/2021
02:00AM
12/03/2021
08:00AM
0 Plant Available
E_LYNE1 12/03/2021
08:18AM
Unplanned Production unavailability - Active 12/03/2021
08:00AM
12/03/2021
09:00AM
0 Plant Available
E_LYNE1 12/03/2021
07:28AM
Unplanned Production unavailability - Dismissed 12/03/2021
08:30AM
12/03/2021
11:00AM
0 Plant Available Event automatically withdrawn.
E_LYNE1 12/03/2021
01:43AM
Unplanned Production unavailability - Dismissed 12/03/2021
07:00AM
12/03/2021
10:00AM
0 Plant Available Event automatically withdrawn.
E_LYNE1 11/03/2021
22:48PM
Unplanned Production unavailability - Active 12/03/2021
05:00AM
12/03/2021
07:00AM
0 Plant Available Event automatically withdrawn.
E_LYNE1 10/03/2021
15:58PM
Unplanned Production unavailability - Active 09/03/2021
10:00AM
11/03/2021
02:00AM
0 Plant Available
E_LYNE1 10/03/2021
15:58PM
Unplanned Production unavailability - Active 11/03/2021
02:00AM
12/03/2021
02:00AM
0
E_LYNE1 03/03/2021
23:08PM
Unplanned Production unavailability - Active 03/03/2021
23:00PM
09/03/2021
00:00AM
0 Boiler
E_LYNE1 03/03/2021
23:08PM
Unplanned Production unavailability - Active 03/03/2021
22:30PM
03/03/2021
23:00PM
0 Plant Available
E_LYNE1 03/03/2021
17:43PM
Unplanned Production unavailability - Active 03/03/2021
17:00PM
03/03/2021
17:30PM
111 Milling Plant
E_LYNE1 03/03/2021
17:43PM
Unplanned Production unavailability - Active 03/03/2021
17:30PM
03/03/2021
21:30PM
100 Milling Plant
E_LYNE1 03/03/2021
17:28PM
Unplanned Production unavailability - Active 03/03/2021
10:00AM
03/03/2021
17:00PM
122 Plant Available
E_LYNE1 03/03/2021
10:23AM
Unplanned Production unavailability - Active 03/03/2021
09:30AM
03/03/2021
10:00AM
120 Plant Available
E_LYNE1 03/03/2021
09:33AM
Unplanned Production unavailability - Active 03/03/2021
08:00AM
03/03/2021
09:30AM
118 Milling Plant
E_LYNE1 03/03/2021
08:28AM
Unplanned Production unavailability - Active 02/03/2021
16:00PM
03/03/2021
08:00AM
122 Plant Available
E_LYNE1 03/03/2021
07:13AM
Unplanned Production unavailability - Dismissed 03/03/2021
17:30PM
03/03/2021
21:00PM
129 Plant Available Event automatically withdrawn.
E_LYNE1 02/03/2021
16:33PM
Unplanned Production unavailability - Active 02/03/2021
12:00PM
02/03/2021
16:00PM
120 Plant Available
E_LYNE1 02/03/2021
12:18PM
Unplanned Production unavailability - Active 02/03/2021
11:30AM
02/03/2021
12:00PM
117 Plant Available
E_LYNE1 02/03/2021
12:18PM
Unplanned Production unavailability - Dismissed 02/03/2021
20:00PM
02/03/2021
22:30PM
92 Plant Available Event automatically withdrawn.
E_LYNE1 02/03/2021
12:03PM
Unplanned Production unavailability - Active 02/03/2021
10:30AM
02/03/2021
11:30AM
115 Plant Available
E_LYNE1 02/03/2021
10:38AM
Unplanned Production unavailability - Active 02/03/2021
08:00AM
02/03/2021
10:30AM
92 Plant Available
E_LYNE1 02/03/2021
08:08AM
Unplanned Production unavailability - Active 01/03/2021
23:30PM
02/03/2021
08:00AM
92 Plant Available
E_LYNE1 02/03/2021
08:08AM
Unplanned Production unavailability - Dismissed 02/03/2021
12:00PM
02/03/2021
13:00PM
125 Plant Available Event automatically withdrawn.
E_LYNE1 02/03/2021
04:28AM
Unplanned Production unavailability - Dismissed 02/03/2021
10:00AM
02/03/2021
11:00AM
122 Plant Available Event automatically withdrawn.
E_LYNE1 01/03/2021
23:43PM
Unplanned Production unavailability - Active 01/03/2021
23:00PM
01/03/2021
23:30PM
95 Plant Available
E_LYNE1 01/03/2021
23:13PM
Unplanned Production unavailability - Active 01/03/2021
22:30PM
01/03/2021
23:00PM
98 Milling Plant
E_LYNE1 01/03/2021
22:48PM
Unplanned Production unavailability - Active 01/03/2021
19:30PM
01/03/2021
22:30PM
122 Plant Available
E_LYNE1 01/03/2021
20:03PM
Unplanned Production unavailability - Active 01/03/2021
11:30AM
01/03/2021
19:30PM
125 Plant Available
E_LYNE1 01/03/2021
11:43AM
Unplanned Production unavailability - Active 01/03/2021
10:30AM
01/03/2021
11:30AM
117 Plant Available
E_LYNE1 01/03/2021
10:48AM
Unplanned Production unavailability - Active 01/03/2021
10:00AM
01/03/2021
10:30AM
113 Plant Available
E_LYNE1 01/03/2021
10:33AM
Unplanned Production unavailability - Active 01/03/2021
09:30AM
01/03/2021
10:00AM
107 Milling Plant
E_LYNE1 01/03/2021
09:43AM
Unplanned Production unavailability - Active 01/03/2021
09:00AM
01/03/2021
09:30AM
112 Plant Available
E_LYNE1 23/02/2021
09:38AM
Planned Production unavailability - Active 03/03/2021
23:00PM
18/03/2021
11:00AM
0 Planned Outage

Planned Outages

Asset ID Available Capacity (MW) Start Date (GMT) End Date (GMT)
Show Archive

Static Data

Asset ID Normal Capacity (MW) Fuel Type Location Market
E_LYNE1 133 Biomass Lynemouth Power GB BETTA Market